In Crore
Taka
|
|
Name of the
Project
|
Project Cost
|
Allocation for
2010-11
|
Expenditure
up to Dec/10
|
Physical
Progress
|
|
1.Guchhogram(Climate Victim
Rehabilitation) project
|
187.29
|
46.16
|
30.20
(65.44%)
|
90 villages have been constructed & 40 villages are
under construction in 75 Upazillas. 3990 land less
families have been allotted houses in those villages & 1875 families will
be allotted houses by June 2011
|
|
2. Study of Detailed Coastal
Land Zoning with two Pilot Districts of Plain Land
project
|
9.81
|
3.28
|
1.10
(33.53%)
|
Upazila-wise Digital Land Zoning Maps have been prepared
for 120 Upazilas.
Draft “Land Use & Management Law” has been prepared,
which will be finalized very soon.
Special Study on Chars and Islands of the coastal area has
been done.
|
|
3. Char Development &
Settlement Project-III.
|
10.12
|
4.24
|
4.24
(100%)
|
128 twin houses and 31 community ponds have been
constructed.
|
|
4. Construction of Upazila
& Union Land Offices (Phase-V) project
|
75.85
|
35.00
|
16.83
(48%)
|
Under this project 55 Upazila land offices and 68 Union
land offices has been constructed so far. Office furniture has been
distributed in 2080 Union Land Offices.
|
|
5. Rehabilitation of scattered
slum dwellers & low income peoples in multistoried building on Govt. land
in Dhaka city.
|
343.65
|
0.36
|
0.08
(23%)
|
Constructions of 10 buildings have been completely done,
and 08 buildings are almost done.
|
|
6. Construction of LATC Hostel Bhaban
|
10.17
|
7.50
|
-
|
Tender invitation process for construction works has been
done.
|
|
7. Strengthening of Settlement
Press, Map printing Press & Preparation of Digital Maps Project
|
18.00
|
-
|
-
|
Project has been approved recently
|